Shift Production Control
SHIFT TIME
04:15 elapsed
07:45 remaining
SHIFT PROGRESS
40%
Status :
🟡 Slightly Behind
Shift Plan (t)
14,200
Total target tonnes
Planned (to Now) (t)
9,450
Prorated plan 66%
Actual (to Now) (t)
8,120
As of current time 57%
Gap (t and %)
-1,330
Vs planned-to-now -14.1%
Run Rate (t/hr)
Current Run Rate
1,250
Required Run Rate
1,650
Current vs required t/hr
End-of-Shift Forecast (t)
17,600
Ton +3,400 pct % +5%

SHIFT DIAGNOSTICS — CONSTRAINT CLASSIFICATION

Hourly trend view for quick constraint classification

Shift Output Trend (total ton)

System Flow
Planned (to-now)
Actual (to-now)

Loading Rate Trend (t/hr)

Loading
Effective Loading Rate
Nominal Baseline

Haul Cycle Time Trend (avg mins)

Haulage
Avg Cycle Time (actual)
Target Baseline

Loaded vs Empty Travel Trend (avg mins)

Travel Split
Loaded Travel
Empty Travel

Dump Wait Time Trend(avg mins)

Dumping
Avg Dump Wait (min)
Baseline

Capacity Sufficiency Trend (capacity surplus/deficit)

Availability
Surplus (+)
Deficit (−)
Zero Line